Major projects of Guiyang and Guian New Area are striving to complete their annual target goals. "Accelerating the construction of major projects is an important support for expanding effective investment and stabilizing the overall economic market," the head of Guiyang Major Project Construction Service Center said.
The Guizhou Aerospace Intelligent Manufacturing Cluster project in Guiyang is divided into two construction phases. Once construction is complete, it will include an R&D pilot area, production area, staff living facilities and other functional blocks.
This year's goal is to complete the capping of each building in Phase 1. At present, 90 percent of the relevant construction has been completed.
The Guizhou Senyang Integrated Circuit Semiconductor Industrial Park project began construction mid-year in 2022. The main work in the development and construction stage is to build standard plants and attract investment.
The annual objective of the Guizhou Senyang project is to finish 70 percent of the main structure of the first batch of standard plants. At present, the project is progressing steadily.
In addition, the Fudi Power Battery Project is currently constructing the main steel structures of six production plants. This is great progress for their goal of putting into production in April 2023.